Contract Number:
2504
Projects:
SAP 086-608-034
Other Projects:
Contract Description:
CSAH 8 Bridge Replacement
Construction Location:
On CSAH 8, 1.7 miles south of CSAH 35 - North Fork Crow River
City of Township:
Marysville

Bid Opening Date & Time:
5/21/2025, 3:00 PM
Award Date:
6/3/2025
Contract Start Date:
6/23/2025
Construction Start Date:
6/23/2025
Construction End Date:
10/31/2025
Work Type:
Aggregate, Bituminous, Bridge, Concrete, Grading, Excavation, Clearing and Grubbing
Project Type:
Bridges
Highest Funding Level:
State
DBE:
No
New Bridge and Approaches
Major Items
NumberDescriptionUnitQuantity
2106.507/00010
EXCAVATION - COMMON
C Y
1205
2106.507/00080
SELECT GRANULAR EMBANKMENT (CV)
C Y
1173
2106.507/00130
COMMON EMBANKMENT (CV)
C Y
1066
2211.507/00170
AGGREGATE BASE (CV) CLASS 5
C Y
711
2360.509/12300
TYPE SP 9.5 WEARING COURSE MIX (2,C)
TON
603
2401.507/03643
STRUCTURAL CONCRETE (3B52)
C Y
80
2401.508/00011
REINFORCEMENT BARS (EPOXY COATED)
LB
42800
2401.518/14001
BRIDGE SLAB CONCRETE (3YHPC-M)
S F
4759
2405.503/00040
PRESTRESSED CONCRETE BEAMS 40MH
L F
659
2406.504/00010
BRIDGE APPROACH PANELS
S Y
190
2442.501/00010
REMOVE EXISTING BRIDGE
LS
1
2452.503/03012
STEEL H-PILING 12"
L F
810
2554.503/00137
TRAFFIC BARRIER DESIGN TRANS TYPE 31
L F
150
2582.503/10204
4" BROKEN LINE PAINT
L F
670
Contract Owner
Messerly, Matthew
3600 Braddock Ave NE
Buffalo, MN   55313
Contract Engineer
Hausmann, Chad
3600 Braddock Avenue NE
Buffalo, MN   55313