Contract Number:
2025-08
Projects:
2025-08
Other Projects:
Contract Description:
Two Rivers Siphon Improvements
Construction Location:
Faribault, MN
City or Township:

Bid Opening Date & Time:
8/5/2026, 4:00 PM
Award Date:
8/12/2026
Contract Start Date:
9/1/2026
Construction Start Date:
9/1/2026
Construction End Date:
7/30/2027
Work Type:
Water Main/Storm Sewer/Sanitary Sewer
Project Type:
Sewer and Water
Highest Funding Level:
Local
DBE:
No
Replacement of sanitary sewer river siphon crossing.
Major Items
NumberDescriptionUnitQuantity
2503.601/00061
SANITARY SEWER BYPASS PUMPING
LS
1
2503.603/13271
27" PVC PIPE SEWER (PS-115)
L F
181
2503.603/36181
18" HDPE PIPE SEWER (IPS, DR11-SIPHON PIPE)
L F
4131
2506.601/06034
CONSTRUCT DRAINAGE STRUCTURE (SA-2 SIPHON MH HEAD)
LS
1
2506.601/06035
CONSTRUCT DRAINAGE STRUCTURE (SA-5 SIPHON MH DISCHARGE)
LS
1
Contract Owner
Duchene, Mark W
208 1st Avenue NW
Faribault, MN   55021
Contract Engineer
Duchene, Mark W
208 1st Avenue NW
Faribault, MN   55021