Contract Number:
032368-000
Projects:
032368-000
Other Projects:
Contract Description:
2026 Resurfacing Project
Construction Location:
Spruce Drive from Buffalo Hills Lane East to South 6th Street Graydon Avenue from Wood Crest Road to Birchridge Drive Hillcrest Drive from Buffalo Hills Lane East to End of Hillcrest Drive Pine Street from SE 16th Street to Walnut Street Dal-Mar Drive & Circle from 1450' East of Beaver Dam Road to End of Dal-Mar Drive & Circle South 11th Street from Thiesse Drive to Industrial Park Road
City or Township:
City of Brainerd, MN

Bid Opening Date & Time:
5/14/2026, 4:00 PM
Award Date:
5/18/2026
Contract Start Date:
5/18/2026
Construction Start Date:
6/15/2026
Construction End Date:
9/18/2026
Work Type:
Aggregate, Bituminous, Grading, Mill and Overlay, Surfacing, Excavation
Project Type:
Road and Street
Highest Funding Level:
Local
DBE:
No
Street resurfacing, drainage, and parking improvements
Major Items
NumberDescriptionUnitQuantity
2104.503/00315
REMOVE CURB & GUTTER
L F
1270
2104.504/00120
REMOVE BITUMINOUS PAVEMENT
S Y
24160
2106.507/00010
EXCAVATION - COMMON
C Y
309
2106.507/00130
COMMON EMBANKMENT (CV)
C Y
33
2360.509/12200
TYPE SP 9.5 WEARING COURSE MIX (2,B)
TON
4810
2503.503/19185
18" RC PIPE SEWER DES 3006 CL V
L F
349
2531.503/02315
CONCRETE CURB & GUTTER DESIGN B618
L F
940
Contract Owner
Youso, Ethan
14275 Golf Course Drive
Baxter, MN   56425
Contract Engineer
Youso, Ethan
14275 Golf Course Drive
Baxter, MN   56425