Contract Number:
02-2026
Projects:
SAP 041-030-021; SAP 041-614-025; SAP 041-615-025; SAP 041-615-026; SAP 041-617-038; CR 113
Other Projects:
Contract Description:
Bituminous Overlay
Construction Location:
SAP 041-030-021 – Patching Plan for various roads in Lincoln County SAP 041-614-025 – CSAH 14 – South Dakota Line to TH 271 SAP 041-615-025 – CSAH 15 – CSAH 1 to TH 75 SAP 041-615-026 – CSAH 15 – CSAH 7 to Lyon County Line SAP 041-617-038 – CSAH 17 – South Dakota Line to Hendricks Main St. County Road 113 – CSAH 7 to 1950’ North
City or Township:

Bid Opening Date & Time:
4/20/2026, 3:15 PM
Award Date:
4/21/2026
Contract Start Date:
5/4/2026
Construction Start Date:
5/4/2026
Construction End Date:
9/4/2026
Work Type:
Aggregate, Bituminous
Project Type:
Road and Street
Highest Funding Level:
State
DBE:
No
Lincoln County Highway Department
Major Items
NumberDescriptionUnitQuantity
2221.609
SHOULDER BASE AGGREGATE CLASS 1 MOD
TON
10750
2232.504
MILL BITUMINOUS SURFACE
SQ YD
3587
2360.509
TYPE SP 12.5 WEARING COURSE MIXTURE (2,B)
TON
25693
2582.503
4" SOLID LINE PAINT
LIN FT
241265
Contract Owner
Lincoln County Highway Department
221 North Wallace Street
Ivanhoe, MN   56142
fax:
507-694-1101
Contract Engineer
Joseph Wilson
221 North Wallace Street
Ivanhoe, MN   56142
fax:
507-694-1101