Contract Number:
26-11
Projects:
26-11
Other Projects:
Contract Description:
2026 Watermain Lining Project
Construction Location:
Southwest corner of Shoreview
City or Township:
Shoreview
Bid Opening Date & Time:
5/13/2026, 3:00 PM
Award Date:
5/18/2026
Contract Start Date:
5/19/2026
Construction Start Date:
5/25/2026
Construction End Date:
10/16/2026
Work Type:
Water Main/Storm Sewer/Sanitary Sewer
Project Type:
Sewer and Water
Highest Funding Level:
Local
DBE:
No
1.1 miles watermain lining in southwest Shoreview in Ramsey County, MN.
| Number | Description | Unit | Quantity |
|---|---|---|---|
2504.602/00806 | 6" GATE VALVE & BOX | EACH | 19 |
2504.602/00808 | 8" GATE VALVE & BOX | EACH | 8 |
2504.603/01062 | 6" WATERMAIN DUCTILE IRON CL 52 | L F | 425 |
2504.603/01082 | 8" WATERMAIN DUCTILE IRON CL 52 | L F | 263 |
2504.608/00015 | WATERMAIN FITTINGS | LB | 3692 |
2611.500 | 6" CIPP WATER MAIN LINING | LIN FT | 2564 |
2611.500 | 8" CIPP WATER MAIN LINING | LIN FT | 3167 |
2611.500 | LINING PIT 10' X 20' | EACH | 12 |
2611.500 | REINSTATE SERVICE CONNECTION | EACH | 79 |
2611.500 | TEMPORARY WATER SERVICE | LUMP SUM | 1 |
Contract Owner
Smith, Stephanie
4600 Victoria Street
ATTN: Engineering Dept
Shoreview, MN 55126
Contract Engineer