Contract Number:
2104 W Superior St R
Projects:
2104
Other Projects:
2104: SP 118-109-021
Contract Description:
W Superior St Reconstruction
Construction Location:
W Superior St - M&H to Carlton St
City or Township:
Bid Opening Date & Time:
4/9/2026, 5:00 AM
Award Date:
4/27/2026
Contract Start Date:
4/27/2026
Construction Start Date:
5/25/2026
Construction End Date:
6/30/2029
Work Type:
Reconstruct
Project Type:
Road and Street
Highest Funding Level:
State
DBE:
Yes
Reconstruction of 1.6 miles of West Superior Street from Carlton Street to Michigan Street. Includes Grading, Bituminous Surfacing, ADA Improvements, Retaining Wall, Lighting, and Signals.