Contract Number:
2603
Projects:
CP 02-26
Other Projects:
Contract Description:
West Side Pavement Striping Project
Construction Location:
The west half of the County.
City or Township:

Bid Opening Date & Time:
4/16/2026, 2:10 PM
Award Date:
4/21/2026
Contract Start Date:
6/18/2026
Construction Start Date:
6/18/2026
Construction End Date:
8/28/2026
Work Type:
Traffic Marking/Striping
Project Type:
Road and Street
Highest Funding Level:
Local
DBE:
No
Maintenance striping on the west side of Murray County.
Major Items
NumberDescriptionUnitQuantity
2582.503
24" SOLID LINE PAINT
L F
689
2582.518
CROSSWALK PAINT
SQ. FT.
90
2582.602
PAVEMENT MESSAGE PAINT
EACH
38
2582.606
4" SOLID/BROKEN LINE PAINT
GAL
1680
2582.606
4" SOLID LINE PAINT
GAL
3907
Contract Owner
Rossow, Keith
1449 State Hwy 30
Slayton, MN   56172
Contract Engineer
Groves, Randy
1449 State Hwy 30
Slayton, MN   56172