Contract Number:
WW-001
Projects:
WW-001 & 25X140731
Other Projects:
WW-001 & 25X140731: WW-001
Contract Description:
2026 Sewer Rehabilitation Project
Construction Location:
Various Locations Marshall MN
1. Wastewater plant 600 West Erie Road
2.Elm Street from North 4th Street to Oak Street.
3. Walnut Street from East College Drive to North 4th Street.
4.East College Drive from Bruce Street to Jewett Street.
5.Bruce Street Backyard to Roosevelt Street.
6.Backyard Easements from Deschepper Street to Gray Place east of Lawrence St., East James Avenue to Robert Street East of Viking Drive, East James Ave. to Robert Street East of Deschepper Street.
City or Township:
Marshall
Bid Opening Date & Time:
2/26/2026, 4:00 PM
Award Date:
3/10/2026
Contract Start Date:
3/9/2026
Construction Start Date:
3/9/2026
Construction End Date:
11/1/2026
Work Type:
Water Main/Storm Sewer/Sanitary Sewer
Project Type:
Sewer and Water
Highest Funding Level:
Local
DBE:
No
The work includes the construction of approximately 4,167 linear feet of 8” CIPP lining, 2,095 linear feet of 10” CIPP lining, 899 linear feet of 12” CIPP lining, 955 linear feet of 18” CIPP lining, 399 linear feet of 24” CIPP lining, 746 linear feet of 30” CIPP lining, the installation of 303.6 vertical feet of SpectraShield Manhole Rehabilitation, 16 Manhole Invert Reconstruction, 105 Lateral Grouting, and all other miscellaneous related work to successfully rehabilitate the existing sanitary sewer system.