Contract Number:
2026STRT-A84 - Sprin
Projects:
STRT2026-A84
Other Projects:
STRT2026-A84: SAP 149-124-003
Contract Description:
Spring Creek Road Reconstruction and Mill Towns State Trail Improvements
Construction Location:
Spring Creek Road between Woodley Street and Huron Court in Northfield
City or Township:
Northfield
Bid Opening Date & Time:
2/5/2026, 8:00 PM
Award Date:
2/17/2026
Contract Start Date:
2/17/2026
Construction Start Date:
3/2/2026
Construction End Date:
11/15/2026
Work Type:
Aggregate, Bituminous, Grading, Pipe and Culvert, Excavation, Clearing and Grubbing
Project Type:
Road and Street
Highest Funding Level:
State
DBE:
No
GRADING, AGGREGATE BASE, PLANT MIXED BITUMINOUS PAVEMENT, CONCRETE CURB AND GUTTER, ADA IMPROVEMENTS, STORM SEWER, WATER MAIN, RELATED APPURTENANCES, STREET LIGHTING, AND BITUMINOUS TRAIL
| Number | Description | Unit | Quantity |
|---|---|---|---|
2101.502/00020 | CLEARING | EACH | 59 |
2106.507/00010 | EXCAVATION - COMMON (CV) | C Y | 5003 |
2360.509/13300 | TYPE SP 9.5 WEARING COURSE MIXTURE (3,C) | TON | 2353 |
2504.603/01122 | 12" WATERMAIN DUCTILE IRON CL 52 | L F | 2260 |
2531.503/02315 | CONCRETE CURB & GUTTER DESIGN B618 | L F | 1390 |
Contract Owner
Contract Engineer