Lift Station 10 Improvements
Construction Location:
County Road 77
City of Township:
City of East Gull Lake
Bid Opening Date & Time:
1/24/2025, 12:00 AM
Award Date:
2/4/2025
Contract Start Date:
2/4/2025
Construction Start Date:
2/4/2025
Construction End Date:
6/27/2025
Work Type:
Water Main/Storm Sewer/Sanitary Sewer
Project Type:
Sewer and Water
Highest Funding Level:
Local
DBE:
No
The furnishing of all labor, materials, tools, and equipment necessary the improvements to Lift Station 10 including replacement of the pumps within the wet well, replacing the influent manhole, lining the influent manhole, replacing of the air release manhole, control panel upgrades for the new lift station pumps, and replacement of the existing light fixture at the lift station on a new pole.
Number | Description | Unit | Quantity |
---|---|---|---|
2104.602 | RELOCATE LIGHTING FIXTURE | EACH | 1 |
2503.501 | CONTROL PANEL AND VFD UPGRADES | LS | 1 |
2503.601/M9498 | SANITARY SEWER BYPASS PUMPING | L S | 1 |
2503.602 | LIFT STATION PUMP REPLACEMENT | EACH | 2 |
2503.602/00200 | AIR RELIEF MANHOLE | EACH | 1 |
2506.503 | CONST 60" DIA SANITARY MANHOLE | EACH | 1 |
2506.603 | MULTI-LAYER POLYMERIC SPRAY LINING REHABILITATION | L F | 12.3 |
2575.601 | SITE RESTORATION | LS | 1 |