Contract Number:
25-4
Projects:
CP 22-78
Other Projects:
Contract Description:
Flood Repair-Embankment Stabilization
Construction Location:
On CR 78, between Crown Ave. and CSAH 5
City of Township:
Bid Opening Date & Time:
8/26/2025, 3:00 PM
Award Date:
9/2/2025
Contract Start Date:
9/15/2025
Construction Start Date:
9/15/2025
Construction End Date:
5/29/2026
Work Type:
Excavation
Project Type:
Road and Street
Highest Funding Level:
State
DBE:
No
On CR 78, Flood Repair - Embankment Stabilization
Number | Description | Unit | Quantity |
---|---|---|---|
2021.501/00010 | MOBILIZATION | LS | 1 |
2451.609/00030 | GRANULAR BACKFILL | TON | 1762 |
2452.602 | TEST SHEET PILE (PZ-22 OR EQUIVALENT) | EACH | 2 |
2452.618 | SHEET PILE (PZ-22 OR EQUIVALENT) | SQ FT | 5775 |
2502.503/09060 | 6" PERF PVC PIPE DRAIN | L F | 215 |
2502.602/00406 | 6" PVC PIPE DRAIN CLEANOUT | EACH | 1 |
2511.509/00012 | RANDOM RIPRAP CLASS II | TON | 80 |
2511.509/00013 | RANDOM RIPRAP CLASS III | TON | 92 |
2563.601/00010 | TRAFFIC CONTROL | LS | 1 |
2574.609/00130 | COMMON TOPSOIL BORROW | TON | 83 |
2575.504/00110 | RAPID STABILIZATION METHOD 4 | S Y | 400 |
Contract Owner
Klisch, Nick
1820 E. Bridge Street
P.O. Box 6
Redwood Falls, MN 56283
Contract Engineer
Klisch, Nick
1820 East Bridge Street
P.O. Box 6
Redwood Falls, MN 56283