Contract Number:
925
Projects:
SAP 014-599-106
Other Projects:
Contract Description:
Twp Bridge EL-35N Removal
Construction Location:
Located on Twp. Rd. 240, 1.5 miles northwest of Baker, MN.
City of Township:
Elmwood
Bid Opening Date & Time:
6/3/2025, 2:00 PM
Award Date:
6/3/2025
Contract Start Date:
6/9/2025
Construction Start Date:
6/9/2025
Construction End Date:
10/17/2025
Work Type:
Bridge, Grading, Excavation
Project Type:
Bridges
Highest Funding Level:
State
DBE:
No
On Township Road 240 Remove Timber beam span bridge No. L8348, Located over Stoney creek, 1.5 miles NW of Baker, MN.
Number | Description | Unit | Quantity |
---|---|---|---|
2106.507/00010 | EXCAVATION - COMMON | C Y | 3000 |
2106.507/00070 | GRANULAR EMBANKMENT (CV) | C Y | 2841 |
2442.501/00010 | REMOVE EXISTING BRIDGE | LS | 1 |
Contract Owner
Clay County Highway Department
2951 41 1/2 St S
Moorhead, MN 56560
Contract Engineer