Contract Number:
03-2025
Projects:
SAP 041-030-020; SAP 041-605-027; SAP 041-607-052; SAP 041-607-053; SAP 041-613-029; SAP 041-620-011; SAP 041-623-004
Other Projects:
Contract Description:
Aggregate Shouldering, Bituminous Surfacing, and Mill and Overlay
Construction Location:
SAP 041-030-020 (Patching Plan for various Locations in Lincoln County); SAP 041-605-027 (CSAH 5 between South Ivanhoe City limits and CSAH 17); SAP 041-607-052 (CSAH 7 between CSAH 17 and CSAH 18); SAP 041-607-053 (CSAH 7 between Northwest Tyler City limits and CSAH 15); SAP 041-613-029 (CSAH 13 between the West County Line and Trunk Highway 75); SAP 041-620-011 (CSAH 20 between Trunk Highway 75 and Yellow Medicine County 16); SAP 041-623-004 (CSAH 23 between State Highway 14 and Railroad Street)
City of Township:

Bid Opening Date & Time:
5/13/2025, 4:00 PM
Award Date:
5/20/2025
Contract Start Date:
5/27/2025
Construction Start Date:
5/27/2025
Construction End Date:
8/1/2025
Work Type:
Aggregate, Bituminous, Mill and Overlay
Project Type:
Road and Street
Highest Funding Level:
State
DBE:
No
Lincoln County Highway Department
Major Items
NumberDescriptionUnitQuantity
2221.609
SHOULDER BASE AGGREGATE CLASS 1 MOD
TON
13996
2232.504
MILL BITUMINOUS SURFACE
SQ YD
112937
2360.509
TYPE SP 12.5 WEARING COURSE MIXTURE (2,B)
TON
37538
2582.503
4" SOLID LINE PAINT
LIN FT
408090
Contract Owner
Lincoln County Highway Department
221 North Wallace Street
Ivanhoe, MN   56142
fax:
507-694-1101
Contract Engineer
Joseph Wilson
221 North Wallace Street
Ivanhoe, MN   56142
fax:
507-694-1101