Contract Number:
2025-04
Projects:
2025-04
Other Projects:
Contract Description:
2025-04 3RD AVE SW STREET RECONSTRUCTION
Construction Location:
3rd Avenue SW Faribault MN
City of Township:
Faribault

Bid Opening Date & Time:
4/16/2025, 4:00 PM
Award Date:
4/22/2025
Contract Start Date:
6/1/2025
Construction Start Date:
6/1/2025
Construction End Date:
8/31/2025
Work Type:
Reconstruct, Water Main/Storm Sewer/Sanitary Sewer
Project Type:
Road and Street
Highest Funding Level:
Local
DBE:
No
Reconstruction
Major Items
NumberDescriptionUnitQuantity
2101.524/00040
CLEARING
TREE
12
2101.524/00050
GRUBBING
TREE
12
2106.607/00010
EXCAVATION - COMMON
C Y
1942
2211.507/00170
AGGREGATE BASE (CV) CLASS 5
C Y
1180
2360.509/13300
TYPE SP 9.5 WEARING COURSE MIX (3,C)
TON
426
2360.509/23200
TYPE SP 12.5 WEARING COURSE MIX (3,B)
TON
560
2503.503/13080
8" PVC PIPE SEWER
L F
1149
2503.503/19125
12" RC PIPE SEWER DES 3006 CL V
L F
295
2503.503/19155
15" RC PIPE SEWER DES 3006 CL V
L F
969
2504.603/02008
8" PVC WATERMAIN
L F
770
2504.603/02012
12" PVC WATERMAIN
L F
434
2506.502/02420
CONST DRAINAGE STRUCTURE DES 48-4020
EACH
9
2521.518/00040
4" CONCRETE WALK
S F
12908
2521.518/00060
6" CONCRETE WALK
S F
3328
2531.503/02315
CONCRETE CURB & GUTTER DESIGN B618
L F
2460
2571.524/05060
CONIFEROUS TREE 6' HT B&B
TREE
4
2571.524/12250
DECIDUOUS TREE 2.5" CAL B&B
TREE
16
2575.504/00011
SODDING TYPE LAWN
S Y
3252