Contract Number:
2025-03
Projects:
2025-03
Other Projects:
2025-03: SAP 125-125-007
Contract Description:
2025 MSA Street Overlay
Construction Location:
Hulett Avenue, Faribault, MN
City of Township:
Faribault

Bid Opening Date & Time:
4/16/2025, 4:00 PM
Award Date:
4/22/2025
Contract Start Date:
6/2/2025
Construction Start Date:
6/2/2025
Construction End Date:
8/31/2025
Work Type:
Mill and Overlay, Water Main/Storm Sewer/Sanitary Sewer
Project Type:
Road and Street
Highest Funding Level:
State
DBE:
No
Mill and Overlay and Watermain Construction
Major Items
NumberDescriptionUnitQuantity
2104.504/00120
REMOVE BITUMINOUS PAVEMENT
S Y
2890
2104.603/01880
MILL BIT SURFACE - CRACK & JOINT REPAIR
L F
670
2232.604/00471
MILL BITUMINOUS SURFACE TYPE 1
S Y
9450
2360.509/23200
TYPE SP 12.5 WEARING COURSE MIX (3,B)
TON
2430
2360.509/23205
TYPE SP 12.5 NON WEAR COURSE MIX (3,B)
TON
420
2360.604/0010
IRREGULAR WIDTH PAVING
S Y
610
2504.602/00010
CONNECT TO EXISTING WATER MAIN
EACH
4
2504.602/00027
INSTALL HYDRANT W/6" LEAD & VALVE
EACH
4
2504.603/02006
6" PVC WATERMAIN
L F
1101
2504.603/02008
8" PVC WATERMAIN
L F
332
2531.503/02320
CONCRETE CURB & GUTTER DESIGN B624
L F
365
2582.503/30404
4" DBLE SOLID LINE MULTI COMP
L F
5092
Contract Owner
Duchene, Mark W
1200 Belview Trail
Faribault, MN   55021
Contract Engineer
Duchene, Mark W
1200 Belview Trail
Faribault, MN   55021