Contract Number:
25-24
Projects:
25-24
Other Projects:
Contract Description:
2025 Inflow and Infiltration Improvement Project
Construction Location:
City of Township:
Bid Opening Date & Time:
2/13/2025, 4:30 PM
Award Date:
3/3/2025
Contract Start Date:
3/4/2025
Construction Start Date:
4/1/2025
Construction End Date:
10/17/2025
Work Type:
Water Main/Storm Sewer/Sanitary Sewer
Project Type:
Sewer and Water
Highest Funding Level:
Local
DBE:
No
Sanitary sewer pipe lining and sanitary manhole lining.
Number | Description | Unit | Quantity |
---|---|---|---|
2 | LINING SEWER PIPE 8" VCP | LF | 3550 |
3 | LINING SEWER PIPE 9" VCP | LF | 10600 |
4 | LINING SEWER PIPE 10" DIP | LF | 385 |
5 | WET WELL MANHOLE LINING | EA | 1 |
Contract Owner
Contract Engineer