Contract Number:
Highway 11 Project -
Projects:
SAP 010-611-027
Other Projects:
SAP 010-611-027: 218931
Contract Description:
Highway 11 Project - Carver Park Reserve
Construction Location:
From 935' S. of TH 7 to 1295' N. of TH 5.
City of Township:

Bid Opening Date & Time:
2/6/2025, 8:00 PM
Award Date:
2/19/2025
Contract Start Date:
3/3/2025
Construction Start Date:
3/3/2025
Construction End Date:
6/1/2026
Work Type:
Reconstruct
Project Type:
Road and Street
Highest Funding Level:
State
DBE:
No
Full Depth Reclamation, Grading, Aggregate Base, Bituminous and Aggregate Surfacing, Culverts, Signing, and Pavement Markings from 935' S. of TH 7 to 1295' N. of TH 5.
Major Items
NumberDescriptionUnitQuantity
2011.601/00018
SETTLEMENT MONITORING
LUMP SUM
1
2021.501/00010
MOBILIZATION
LUMP SUM
1
2104.504/00120
REMOVE BITUMINOUS PAVEMENT
SQ YD
13317
2106.507/00010
EXCAVATION - COMMON
CU YD
45488
2106.507/00130
COMMON EMBANKMENT (CV)
CU YD
93774
2118.507/00120
AGGREGATE SURFACING (CV) CLASS 2
CU YD
2192
2211.507/00170
AGGREGATE BASE (CV) CLASS 5
CU YD
11597
2215.504/00010
FULL DEPTH RECLAMATION
SQ YD
23853
2360.509/13300
TYPE SP 9.5 WEARING COURSE MIX (3,C)
TON
11682
2360.509/23205
TYPE SP 12.5 NON WEAR COURSE MIX (3,B)
TON
5238
2502.503/07060
6" PE PIPE DRAIN
LIN FT
2866
2502.503/10060
6" PERF PE PIPE DRAIN
LIN FT
6611
2503.602/00150
LIFT STATION
EACH
1
2503.602/00190
STANDARD VALVE MANHOLE
EACH
1
2503.603/25004
4" PVC FORCE MAIN
LIN FT
1950
2506.503/00190
CONST DRAINAGE STRUCTURE DESIGN SD-48
LIN FT
46.6
2506.601/00011
CONSTRUCT LIFT STATION
LUMP SUM
1
2506.602/06120
INSTALL MANHOLE
EACH
2
2521.518/00130
3" BITUMINOUS WALK
SQ FT
40788
2545.502/21100
SERVICE CABINET
EACH
1
2563.601/00010
TRAFFIC CONTROL
LUMP SUM
1
Contract Owner
Van Oort, Jordan
11360 US Route 212
Suite 1
Cologne, MN   55322
Contract Engineer
Fackler, Carolyn
11360 US Route 212
Suite 1
Cologne, MN   55322