Contract Number:
22007
Projects:
CP 71-613-022
Other Projects:
CP 71-613-022, CP 71-637-021, CP 71-662-023, CP 71-676-022, TWP 20-2025-01
Contract Description:
2025 Resurfacings
Construction Location:
CSAH 13 from CSAH 12 to Line Avenue
CR 37 from 325th Ave to E Co Line
CR 62 from CSAH 20 to CSAH 6
CR 76 from CSAH 8 to State St
Clear Lake Twp White Farm Estates
City of Township:
Bid Opening Date & Time:
4/3/2025, 6:00 PM
Award Date:
4/15/2025
Contract Start Date:
5/19/2025
Construction Start Date:
5/19/2025
Construction End Date:
7/18/2025
Work Type:
Bituminous, Mill and Overlay
Project Type:
Road and Street
Highest Funding Level:
Local
DBE:
No
Pavement resurfacings on CSAH 13, CR 37, CR 62 CR 76 and roads located in Clear Lake Twp's White Farm Estates development
Number | Description | Unit | Quantity |
---|
No data available
Contract Owner
Contract Engineer
Roedel, David A
13880 Business Center Dr
Elk River, MN 55330